The short answer
Start with the reference point and the instrument. Then look for patterns: a low corner, a high center, a ridge or trough along one line. Adjust for floor coverings. Compare the readings with visible distress. Be cautious with steep differences over short distances, which the ASCE Texas Section guidelines warn can reflect built-in unevenness. And remember that one survey shows shape, not change.
The reference point
Every survey picks a reference point, usually set to zero, and reports other points as higher or lower. The choice changes how the numbers look but not the shape they describe. A good survey states where the reference is and which instrument was used.
Common patterns
One low corner or side. Often associated with localized drying, such as from a nearby tree, or with settlement at that edge.
High center, low edges. Consistent with center lift, when perimeter soil has dried and shrunk.
Low center, high edges. Consistent with edge lift after perimeter wetting.
A localized low area inside the slab. May point to a plumbing leak or soil loss in that area, which is why engineers sometimes add plumbing tests in a Level C investigation. Home Inspection Dallas explains the warning signs of slab leaks for buyers.
Patterns are hypotheses. The engineer tests them against distress, history and, if needed, testing.
Floor coverings
Tile on a mortar bed sits higher than carpet; wood flooring sits at its own height. A survey taken on finished floors should note the covering at each point, or adjust for it, before calculating anything.
Built-in unevenness
No slab or framed floor is built perfectly flat. The guidelines caution engineers to use care over distances under about 20 feet, where construction tolerance can dominate. A survey that shows a one-inch difference between two points three feet apart may describe a thickened tile bed, not movement.
Turning numbers into criteria
Engineers calculate deflection and tilt from the readings and compare them with yardsticks such as the L/360 deflection ratio and the observation that tilt above 1 percent is usually noticeable. The guidelines require symptoms alongside the numbers before concluding that deflection is excessive.
Comparing surveys
Change is what matters most. Compare a new survey with an older one only if the reference point, the instrument and the coverings are known. A seller's post-repair survey, compared with a buyer's new survey, shows whether the house has moved since repair. The guidelines recommend engineers keep post-repair elevations for exactly that purpose.
Who interprets it
A licensed professional engineer. Repair companies take readings when preparing estimates, which is useful information from a party that sells the repair.
Common misreadings
"The biggest number is the problem." Pattern and distance matter more.
"Zero is level." Zero is only the reference point.
What a survey cannot show
An elevation survey measures the floor surface on one day. It does not show the shape the slab was built in, how fast it is moving, or why. It cannot see under the slab, so it says nothing directly about plumbing, voids or tendon condition. It also cannot separate a framing problem from a foundation problem on a pier and beam house without the engineer looking at the structure. That is why engineers combine the survey with history, visible distress and, where needed, testing. A survey read on its own, especially one taken by a party that sells repairs, is a starting point for questions rather than an answer.
Where the facts come from
ASCE Texas Section Guidelines, Version 3; PTI literature on edge lift and center lift; TREC standards on elevation measurement.