The short answer
Engineers design residential slabs on expansive soil by modeling how the clay will swell or shrink at the edges and center of the slab, then sizing the slab, its beams and its reinforcement to resist the resulting bending. Post-tensioned slabs, the usual North Texas choice, follow the Post-Tensioning Institute's DC10.5 standard. Conventionally reinforced slabs follow a different method. Many DFW cities require an engineer's letter or sealed plans for new foundations.
Center lift and edge lift
On expansive clay, moisture changes most at the edges of a slab, where the soil is exposed to rain and sun. In a wet period the edges can swell up relative to the center, called edge lift. In a dry period the edges can shrink and drop, leaving the center high, called center lift. The design has to handle both. PTI's literature on slab design describes these conditions and the soil parameters engineers use to estimate them.
Post-tensioned slabs
The Post-Tensioning Institute describes post-tensioned slabs-on-ground as a cost-efficient, high-performance solution for shrink-swell soils, with added stiffness that controls deflection. Engineers design them under PTI DC10.5, Standard Requirements for Design and Analysis of Shallow Post-Tensioned Concrete Foundations on Expansive and Stable Soils. STRUCTURE magazine notes that the 2024 International Residential Code references DC10.5 directly. A draft of the next edition, DC10.5-24, was released for public comment in November 2024.
Conventionally reinforced slabs
PTI Technical Note 21 explains that nonprestressed slabs on expansive soils are designed by the WRI/CRSI Design of Slab-on-Ground Foundations method, and that residential post-tensioned slabs were never intended to fall under the ACI 318 building code. The two methods aim at the same outcome with different reinforcement.
The soil inputs
Design starts with soil testing. Geotechnical engineers sample the lot or subdivision and report values such as the plasticity index and, often, potential vertical rise. Those feed the design parameters for edge and center movement.
What cities ask for
Many DFW cities require engineered foundation plans for new houses. Fort Worth states that all new residential permits must have an engineered foundation plan. Dallas's residential checklist says a post-tensioned slab is required to be engineered and submitted with an engineering letter. Carrollton asks for an engineer's letter indicating the soil information and codes used to design the foundation.
What a buyer can collect
For a newer house, the foundation plans and the engineer's design letter may be in the city's permit file or with the builder. Those documents show the slab type, the design method, the soil values used and the engineer of record. They are the baseline any later evaluation will be compared against.
Common misreadings
"Designed for clay means it won't move." Design limits movement to tolerable levels; it does not stop the soil.
"A newer standard means my older slab is unsafe." Codes change; performance is judged on the house.
Where the facts come from
PTI, slab-on-ground applications, DC10.5 and Technical Note 21; STRUCTURE magazine on IRC references; Fort Worth, Dallas and Carrollton permit checklists.